Sedona Airport, AZ, New Fuel Farm

Key Info

Project Details

Two symmetrical orange arrows pointing right, forming a square with a white diagonal cross.
Delivery Method Design-Bid-Build
 

The Sedona Oak Creek Airport Authority contracted KEAR to provide fuel farm upgrades and replacement at Sedona Airport.  The project included two new 15,000-gallon and one new 12,000-gallon double-walled, UL 2085 aboveground storage tanks. KEAR also installed access platforms and stairs, bulk fuel loading skids, fuel system piping and supports, containment and storm drain piping, and electrical and control systems. Site improvements included a new concrete containment basin and a concrete and asphalt access drive. The project also included startup and commissioning of the fuel system.